Step 1 Study of the drawings
-we study all the Architect, RCC drawings finishing drawings of the building before starting the building construction work, after study of drawings we next do site preparation workStep 2 Site Preparation Work
-As per the drawing, plot area is marked on the field Construction process of building/House
-The Building construction site needs to do cleaning work before the excavation work is executed.
-The removal of debris, cutting of trees, other unwanted materials removed from the site.
-After Cleaning nee to do leveling work of the groundStep 3 Excavation Work
-As per building foundation drawings, starts excavation of the ground.
-Excavation work is done with the help of excavating machines such as JCB, Poclain,etc DND Construction and manually with the help of labors by Hoe or shovels,etc.
-Excavation work done till hard strata is visible.Step-4 PCC (Plain Cement Concrete) work
-We remove all excavated materials from the site and cleaning is done properly.
-Concrete low grades like M10, M12.5, or M15 is used for PCC work.Step 5 Foundation Work
-A foundation is a lowermost part of a building structure that transfers all building load to the earth.
Foundation work of activity includes
-Reinforcement work of footings
-Shuttering work of footing
-Concrete Pouring work of footings
As per the above steps we complete all footing work as per RCC drawingsStep-6 Backfilling work
-Backfilling is the process of filling the excavated Plinth or trenches after the construction of footing.
-Plinth filling is done to fill the area within the Plinth.
-Soil well compacted before starting the plinth workStep 7 Plinth beam and slab work
-Plinth beam and slab make the structured composite
-Plinth beam is a reinforced concrete beam constructed between the wall and its foundation.
-The plinth beam is provided to prevent the extension or propagation of cracks from the foundation into the wall above when the foundation suffers from the settlement.
-Plinth beams distribute the load of the wall over the foundation evenly.Step 8 Column Construction Work
-Column is a vertical structural member of building that carry loads mainly in compression.
 construction activity of column as follows
-Reinforcement work of column
-Shuttering work of column
-Concrete Pouring work of columnStep 9 Slab Construction work
-A slab is a structural element, made of concrete, that is used to create flat horizontal surfaces such as floors, roof decks, and ceilings.
-Reinforcement work of slab
-Shuttering work of slab
-Concrete Pouring work of slabThis is how Residential building Construction activities of step by step going on-site. this step varies as per site conditions, these are the basic sequence of activities
Send your opinions and suggestions to email id:dndconstructioncompany@gmail.comThank you. watch this full video on youtubehttps://www.youtube.com/watch?v=Q0m0EQoDmkk

Published by Civil Engineering Knowledge by DND Construction

DND Construction is a Learning Platform for Civil engineers and Construction work-related people

Leave a comment

Design a site like this with WordPress.com
Get started